UPS systems carry the load when grid power falters — and IS 16242 / IEC 62040 ensure that the very moment the building loses power, the UPS does not fail too. As an NABL accredited testing laboratory recognised by BIS and TEC, Matrix Test Labs delivers uninterruptible power systems (ups) testing that is accepted by Indian regulators, OEMs and international buyers alike. Our laboratory in Delhi combines calibrated infrastructure with engineers who live and breathe these standards every day.
Whether you are an established brand putting a new generation of uninterruptible power systems (UPS) on the market, an importer chasing BIS compliance, or an R&D team validating a fresh design, our test reports give you the confidence to launch — and the documentation to defend that launch in front of any regulator or auditor.
Our scope of NABL accreditation is reviewed every cycle to keep pace with revisions in IS, IEC, AIS and TEC specifications, so the test report we hand you today is the one your homologation committee will accept tomorrow.
Each parameter is executed under controlled environmental conditions on calibrated equipment with full traceability to national reference standards. Test data is captured digitally, reviewed by a qualified test engineer and signed off by an authorised signatory before the report leaves the laboratory.
Matrix Test Labs is one of the few independent third-party laboratories in Delhi that combines NABL accreditation, BIS recognition and TEC empanelment under a single roof. That means an uninterruptible power systems (UPS) test request submitted at our gate can move through electrical safety, mechanical safety, environmental qualification and, where applicable, performance benchmarking without ever leaving the campus — cutting weeks from your typical product release timeline.
Our engineering team is fluent in IS, IEC, AIS, TEC and EN standards, and we offer pre-compliance support so that the first formal test sequence is also the last one you have to pay for. From a single component verification to a complete certification dossier, every engagement begins with a free scoping call to map your specific uninterruptible power systems (UPS) against the applicable standards.
Typical turnaround for a complete uninterruptible power systems (ups) testing sequence is 3 to 6 weeks, depending on sample availability and the depth of the test plan. Express slots are available for urgent homologation deadlines. Final reports are delivered as digital, signed PDFs along with a hard copy and supporting raw data on request. Every test report carries the NABL emblem along with our laboratory accreditation number, making it readily acceptable to BIS certification bodies, TEC, ARAI, ICAT, regulatory authorities and overseas buyers.
To begin uninterruptible power systems (ups) testing, you will typically need to submit between 3 and 8 representative samples of the uninterruptible power systems (UPS) along with their technical datasheet, declared ratings, circuit diagrams and a copy of the user manual. Our laboratory coordinator will confirm the exact sample quantity once the scope is finalised. Samples can be hand-delivered to our Delhi facility, sent by courier with our consignment note, or collected on request within Delhi-NCR. Each sample is uniquely barcoded on arrival and tracked through the testing pipeline, giving you full visibility on progress at every stage.
Will the test report be accepted by BIS / TEC / ARAI? Yes — because our laboratory is NABL accredited and recognised under the relevant Indian schemes, reports from Matrix Test Labs are accepted by all major Indian certification bodies and regulatory authorities for uninterruptible power systems (UPS).
Do you offer pre-compliance testing? Absolutely. We routinely run a pre-compliance sweep on prototype units so design teams can correct issues before the formal uninterruptible power systems (ups) testing sequence begins, eliminating expensive re-test cycles.
Can you help with retest after a design change? Yes — partial retests against affected clauses are scoped on a case-by-case basis and usually cost a fraction of a full sequence.
Talk to our team today to scope your uninterruptible power systems (ups) testing project. Call +91 73032 50578, write to sales@matrixtestlabs.com, or use the contact form on this site — we usually respond within one working day with a draft test plan, indicative pricing and a target start date for your uninterruptible power systems (UPS).
| Test Parameter | Standard / Clause | Requirement |
|---|---|---|
| Touch current | IEC 62040-1 cl. 5 | ≤ 0.25 mA |
| Electric strength | IEC 62040-1 cl. 5 | 2U + 1000 V |
| Heating | IEC 62040-1 cl. 6 | Per declared |
| Switching | IEC 62040-3 cl. 5 | Transfer ≤ 10 ms |
| Battery test | IEC 62040-3 cl. 6 | Rated runtime at full load |
| Abnormal operation | IEC 62040-1 cl. 5 | Overload, short, open |
| Mechanical strength | IEC 62040-1 cl. 7 | 250 N steady |
| Harmonic emissions | IEC 61000-3-2 / 3-4 | Within class limits |
Send us your product details and we'll get back to you with a quotation and timeline.
NABL Accredited & BIS Recognised — fast turnaround, reliable results.